MYTILINEOS SA announces the signing of a contract with JAVNO PODJETJE
ENERGETIKA LJUBLJANA, Ljubljana’s energy company, engaged in electrical
and thermal production, transmission and distribution, operating Slovenia’s largest
District Heating System.
The contract involves the Engineering, Procurement and Construction of a new
Combined Heat and Power (CHP) plant in Ljubljana, Slovenia, substituting to a
large extent coal with natural gas, thus reducing coal consumption by 70%.
The scope of the project includes the supply, installation and commissioning of 2
Siemens gas turbines and 2 heat recovery steam generators with pertaining
equipment, including all necessary construction works and pipeline connections to
the existing steam turbine and to the points of contact with the remaining existing
devices.
The project will be completed within 30 months post the project’s commencement
date, which, subject to normal permitting procedures, will be within the 1st half of
this year.
The signing of the agreement was held on 03.04.2019 at a special ceremony in
Ljubljana, Slovenia.
This new dual fuel (natural gas or extra light fuel oil) combined heat and power
plant with total electrical power output of 110MW, is expected to make a vital
contribution to meeting the electricity and district / process heating needs of
Ljubljana’s citizens.
The contract value for MYTILINEOS amounts to 118 million euros.