The main characteristics of this new project are as follows:
1. Project Owner:
Société Algérienne de Production de l’Electricité (SPE Spa). SPE is part of the Sonelgaz Group, the major Algerian electricity utility.
2. Project Description:
The project concerns the engineering, procurement, installation and commissioning of eight (8) mobile gas turbine power generation units with a total output of 179,72 MW at site conditions, to be installed at three (3) sites in Algeria.
3. Award Value:
The total contract value for Power Projects Limited is USD 66.085.842.
4. Project Time Schedule:
The project will be carried out on a fast-track schedule, with commercial operation in the first half of 2014.